After fixing the plane table to the tripod, the main operations which are needed at each plane table station are ______________ ?
1. levelling
2. orientation
3. centering
The correct sequence of these operations is
Options:
A .  (1), (2),(3)
B .  (1), (3), (2)
C .  (3), (1), (2)
D .  (2), (3), (1)
Answer: Option B
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!