A milestone chart
Options:
A .   Shows the inter dependences of various jobs
B .   Depicts the delay of jobs, if any
C .   Points outgoing ahead of schedule of jobs, if any
D .   None of the above
Answer: Option D
Explanation :

Was this answer helpful ?
Next Question

Submit Solution