Sail E0 Webinar
Question
400 cumecs of water are being released from dam storage to meet the downstream demand through the turbines of the connected hydro plant. The effective head of water acting on the turbines is 50 m. The efficiency of the hydro plant is 0.8. The electrical power generated from this plant is __________________
Options:
A .  1,56,800 MW
B .  156.8 M kW
C .  156.8 MW
D .  156.8 kW
Answer: Option C
Answer: (c).156.8 MW

Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers