Question 31. The probability distribution of activity times in PERT follows following distribution
  1.    Normal
  2.    Binomial
  3.    Beta
  4.    Exponential
 Discuss Question
Answer: Option C. -> Beta
Question 32. The probability distribution of project completion in PERT follows following distribution
  1.    Normal
  2.    Binomial
  3.    Exponential
  4.    Gaussian
 Discuss Question
Answer: Option D. -> Gaussian
Question 33. If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be
  1.    2 HA
  2.    1.33 HA
  3.    1.5 HA
  4.    1.15 HA
 Discuss Question
Answer: Option A. -> 2 HA
Question 34. In order to avoid excessive multiplication of facilities, the layout preferred is
  1.    Product layout
  2.    Process layout
  3.    Group layout
  4.    Static layout
 Discuss Question
Answer: Option B. -> Process layout
Question 35. Actual performance of a task is called
  1.    An event
  2.    An activity
  3.    A duration
  4.    None of these
 Discuss Question
Answer: Option B. -> An activity
Question 36. The essential condition for the decompression of an activity is that
  1.    The project time should change due to decompression
  2.    After decompression the time of an activity invariably exceeds its normal time
  3.    An activity could be decompressed to the maximum extent of its normal time
  4.    None of the above
 Discuss Question
Answer: Option C. -> An activity could be decompressed to the maximum extent of its normal time
Question 37. According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum)
  1.    CAM < DAM
  2.    CAM > DAM
  3.    CAM = DAM
  4.    There is no such criterion
 Discuss Question
Answer: Option A. -> CAM < DAM
Question 38. The simplex method is the basic method for
  1.    Value analysis
  2.    Operation research
  3.    Linear programming
  4.    Model analysis
 Discuss Question
Answer: Option C. -> Linear programming
Question 39. Bar charts are suitable for
  1.    Minor works
  2.    Major works
  3.    Large projects
  4.    All of the above
 Discuss Question
Answer: Option A. -> Minor works
Question 40. 'O' on a PERT/CPM chart represents
  1.    An ordinary event
  2.    A significant event representing some milestone
  3.    An event to be transferred to other network chart
  4.    Dangling event
 Discuss Question
Answer: Option A. -> An ordinary event