Which of the following statement is correct?
Options:
A .   When slack of an activity is zero, it falls only on critical path.
B .   CPM technique is useful to minimize the direct and indirect expenses.
C .   Critical path of a net work represents the minimum time required for completion of project.
D .   All of the above
Answer: Option D
Explanation :

Was this answer helpful ?