Question
Which of the following is not a part of process change ?
Options:
A .  Introducing new practices, methods or processes
B .  Introducing new team members to existing project
C .  Introducing or removing deliverable
D .  Introducing new roles or responsibilities
Answer: Option B
ADDING MORE DEVELOPERS AID TO PROCESS COMPLETION RATHER THAN CHANGING IT.