Sail E0 Webinar
Question
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as
Options:
A .  Duration
B .  Total float
C .  Free float
D .  Interfering float
Answer: Option C

Submit Your Solution Below and Earn Points !
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers