Mobilization advance up to 10% of the cost of work is given to a contractor
Options:
A .  On commencement of work at site for payment of loan taken by him
B .  For the purchase of construction materials
C .  For the payment of advances to labour and other staff
D .  For all activities required to start the work at site on finalization of the contract document
Answer: Option D