Under normal conditions using an ordinary cement, the period of removal of the form work, is :



Options:
A .  7 days for beam soffits
B .  14 days for bottom slabs of spans 4.6 m and more
C .  21 days for bottom beams over 6 m spans
D .  2 days for vertical sides of columnsE. all the above.
Answer: Option A