Sail E0 Webinar
Question
Pick up the correct statement from the followingPick Up The Correct Statement From The Following
Options:
A .  In a level crossing, a crest with its top at the canal F.S.L. is provided across the drainage at its up-stream junction with canal
B .  In a level crossing a regulator is provided across the drainage at its down-stream
C .  In a level crossing, a cross regulator is provided on the canal below the crossing
D .  All the above.
Answer: Option D
Answer: (d).All the above.

Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers