Question

Pick up the correct statement from the following



Options:
A .  In a level crossing, a crest with its top at the canal F.S.L. is provided across the drainage at its up-stream junction with canal
B .  . In a level crossing a regulator is provided across the drainage at its down-stream
C .  In a level crossing, a cross regulator is provided on the canal below the crossing
D .  All the above.
Answer: Option D