If the processes cannot take place simultaneously, what is the minimum time (In hours) required to get one unit of the final product?
ProcessProcess(es) to be completed before the process in column 1P−QP,RR−SQTQ,SUY,T,VVSWV,XXSYP,R
___
Answer: Option A
:
Final product is achieved if any of U or W is completed.
To complete U:
P + R + Q + S + T + Y + V + U = 6 + 4 + 7 + 2 + 4 + 14 + 3 + 10 = 50 hours
To complete W:
P + R + Q + S + V + X + W = 6 + 4 + 7 + 2 + 3 + 7 + 9 = 38 hours
Was this answer helpful ?
:
Final product is achieved if any of U or W is completed.
To complete U:
P + R + Q + S + T + Y + V + U = 6 + 4 + 7 + 2 + 4 + 14 + 3 + 10 = 50 hours
To complete W:
P + R + Q + S + V + X + W = 6 + 4 + 7 + 2 + 3 + 7 + 9 = 38 hours
∴ The minimum time required to get one unit of final product is 38 hours.