Sail E0 Webinar
Question


If the Organizers want to ensure that all participants travelling from S to T take the same time (travelling time and task time combined) regardless of the route they choose and the street from B to C is under repairs (and hence unusable), then a feasible set of task time (in hours) at junctions A, B, C, and D respectively to achieve this goal is:
If The Organizers Want To Ensure That All Participants Trave...


Options:
A .   2,5,3,2
B .   0,5,3,1
C .   1,5,3,2
D .   Both (b) and (c)
Answer: Option D
:
D

As B - C is unusable, S - B - C - T is not possible.
The other possible ways are : S - A - T,  S - B - A - T , S - D - T, and S - D - C - T 
From these if we apply all the options:
Both option (b) and (c) are true, as in both the cases total time is same for each of the four routes.



Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

More Questions on This Topic :

Latest Videos

Latest Test Papers