Sail E0 Webinar
Question
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
Options:
A .  EF = ES + D
B .  LS = LFD
C .  LF = LS + D
D .  All of the above
Answer: Option D