Activity slack or float of any event on a PERT/CPM chart is represented by
Options:
A .  Latest start time of succeeding event earliest finish time of preceding event activity time
B .  Latest start time of the event earliest start time of the event
C .  Latest finish time of event earliest finish time of the event
D .  Anyone of the above
Answer: Option D