Sail E0 Webinar

Quantitative Aptitude

TIME AND WORK MCQs

Time & Work, Work And Wages

Total Questions : 1512 | Page 3 of 152 pages
Question 21.

  1. 3 men can do a piece of work in 6 days. After 2 days 3 more men joined them. How many days will they take to complete the remaining work?

  1.    2 days
  2.    3 days
  3.    4 days
  4.    5 days
 Discuss Question
Answer: Option A. -> 2 days
Question 22.

  1. How many days will 12 women take to do a piece of work which 10 men take 15 days to complete, if 3 women do as much work as 2 men?

  1.    16.75
  2.    17.75
  3.    18.75
  4.     none of these
 Discuss Question
Answer: Option C. -> 18.75
Question 23.

  1. To do a certain piece of work, B would take three times as long as A and C together, and C twice as long as A and B together. The three men together can complete the work in 10 days. How long would A, B and C separately take to complete the work (in days)?

  1.    20 , 30 , 40
  2.    24 , 40 , 30
  3.    30 , 40 , 24
  4.    40 , 30 , 20
 Discuss Question
Answer: Option B. -> 24 , 40 , 30
Question 24.

  1. If 12 men and 16 boys can do a piece of work in 5 days and 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it?

  1.    8 days
  2.    \(8\frac{1}{3}\) days
  3.    9 days
  4.    \(9\frac{1}{3}\) days
 Discuss Question
Answer: Option B. -> \(8\frac{1}{3}\) days
Question 25.

  1. A and B working alone can finish a piece of work in 8 and 7 days respectively. If they work at it alternately for a day, A beginning, in how many days will the work be finished?

  1.    \(6\frac{1}{2}days\)
  2.    7 days
  3.    \(7\frac{1}{2}days\)
  4.    8 days
 Discuss Question
Answer: Option C. -> \(7\frac{1}{2}days\)
Question 26.

  1. Twenty men can finish a piece of work in 30 days. After how many days should 5 men leave, so that the work may be finished in 35 days?

  1.    9 days
  2.    12 days
  3.    15 days
  4.    18 days
 Discuss Question
Answer: Option C. -> 15 days
Question 27.

  1. A is thrice as good a workman as B. He is able to finish a piece of work in 60 days less than B. Find the time in which they can do it working together.

  1.    \(22\frac{1}{2}\)  days
  2.    25 days
  3.    \(27\frac{1}{2}\)
  4.    30 days
 Discuss Question
Answer: Option A. -> \(22\frac{1}{2}\)  days
Question 28.
  1. After working for 6 days, Ashok finds that only 1/3rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?

  1.    19 days
  2.    20 days
  3.    21 days
  4.    22 days
 Discuss Question
Answer: Option B. -> 20 days
To solve this problem, we first need to calculate Ashok's efficiency in terms of work done per day. If Ashok worked for 6 days and only 1/3rd of the work has been done, then his efficiency can be calculated as follows:
Work done by Ashok in 6 days = 1/3 of the total workWork done by Ashok per day = 1/3 of the total work ÷ 6 days = 1/18 of the total work
Next, we need to calculate Ravi's efficiency in terms of work done per day. Ravi is 60% as efficient as Ashok, so his efficiency can be calculated as follows:
Work done by Ravi per day = 60% of Ashok's efficiency = 60% of 1/18 of the total work
Finally, we need to calculate the number of days Ravi would take to complete the remaining 2/3rd of the work. We can use the formula:
Time taken by Ravi to complete the work = Remaining work ÷ Ravi's efficiency per day
Substituting the values, we get:
Time taken by Ravi to complete the work = 2/3 of the total work ÷ (60% of 1/18 of the total work) = 20 days
Here is a summary of the key points in bullet form:
  • Ashok worked for 6 days and only 1/3rd of the work has been done, so his efficiency per day can be calculated as 1/18 of the total work.
  • Ravi is 60% as efficient as Ashok, so his efficiency per day can be calculated as 60% of 1/18 of the total work.
  • The time taken by Ravi to complete the remaining 2/3rd of the work can be calculated using the formula: Remaining work ÷ Ravi's efficiency per day = 20 days.
In conclusion, the correct answer is Option B, "20 days."
Question 29.

  1. A and B can do a job in 15 days and 10 days respectively. They begin the work together but A leaves after some days and B finishes the remaining work in 5 days. After how many days does A leave?

  1.    3 days
  2.    4 days
  3.    5 days
  4.    6 days
 Discuss Question
Answer: Option A. -> 3 days
Question 30.
  1. A group of workers engaged in plastering a tank completed 1/2 of the work in one day and 1/3rd of the remaining work on the next day. If still 60 square metres of the tank remain to be plastered, find the area of the tank that is to be plastered.

  1.    170 sq. m
  2.    180 sq. m
  3.    190 sq. m
  4.    none of these
 Discuss Question
Answer: Option B. -> 180 sq. m
Let the total area of the tank be 'A' square metres, and the area of the plastered portion of the tank be 'x' square metres. Therefore, the remaining area to be plastered is (A - x) square metres.
Given that the workers completed 1/2 of the work in one day, therefore the plastered area on the first day is (1/2)*A.
The remaining area to be plastered after the first day is (A - (1/2)*A) = (1/2)*A.
Given that the workers completed 1/3rd of the remaining work on the next day, therefore the area plastered on the second day is (1/3)*((1/2)*A) = (1/6)*A.
The total area plastered is the sum of the areas plastered on both days, i.e.,
x = (1/2)*A + (1/6)*A = (2/3)*A.
The area remaining to be plastered is given as 60 square metres, i.e.,
A - x = 60.
Substituting the value of x from above, we get:
A - (2/3)*A = 60,
which gives us (1/3)*A = 60.
Therefore, the total area of the tank is:
A = 180 square metres.
Hence, the area of the tank that is to be plastered is:
(A - x) = A - (2/3)*A = (1/3)A = 60(3) = 180 square metres.
Therefore, option B, i.e., 180 sq. m is the correct answer.If you think the solution is wrong then please provide your own solution below in the comments section .

Latest Videos

Latest Test Papers