Sail E0 Webinar

MCQs

Total Questions : 20 | Page 1 of 2 pages
Question 1. In CIF integration model, to transfer data from R/3 system to SAP SCM what is PDS usage type?
  1.    PP/DS
  2.    PP/DS subcontracting
  3.    SNP & SNP subcontracting
  4.    None of the above
 Discuss Question
Answer: Option C. -> SNP & SNP subcontracting




Question 2. Which of the following is the LEAST important reason supply managers need to forecast?
  1.    Technology, design, cost, co-development, quality, intellectual property and risk management
  2.    Delivery, cost and quality
  3.    Supplier contract and relationship
  4.    The suppliers history with the buying company
 Discuss Question
Answer: Option C. -> Supplier contract and relationship




Question 3. The PRIMARY objective of asset recovery is to:
  1.    Minimize the environmental impact of the asset's disposal
  2.    Classify and monitor an asset throughout its life cycle
  3.    Re-employ or reuse a surplus asset of value
  4.    Optimize return on the asset
 Discuss Question
Answer: Option D. -> Optimize return on the asset




Question 4. Supply management organizations must develop tools and processes to audit compliance. The MOST important reason for such processes and tools is to:
  1.    Meet the needs of the audit group of corporate headquarters
  2.    Ensure standardization of policies throughout the supply management organization
  3.    Provide a benchmark for the company to use when working with other organizations within the same industry
  4.    Ensure results of actions and decisions of the supply management organization can be measured and improved as required
 Discuss Question
Answer: Option D. -> Ensure results of actions and decisions of the supply management organization can be measured and improved as required




Question 5. Which of the following doesn't affect Supply Chain process?
  1.    More Competition in Market
  2.    Less number of suppliers
  3.    Increased Opportunities
  4.    Longer Product Lifecycles
 Discuss Question
Answer: Option D. -> Longer Product Lifecycles




Question 6. A Supply Chain is a process of linking?
  1.    Suppliers and Manufacturers
  2.    Suppliers and Dealers
  3.    Suppliers and Consumers
  4.    Customer and products
 Discuss Question
Answer: Option C. -> Suppliers and Consumers




Question 7. Which of the following is NOT a consideration in developing a ramp-up strategy for new product introduction?
  1.    Sales projections
  2.    Capacity requirements
  3.    Early supplier involvement (ESI)
  4.    Staffing requirements
 Discuss Question
Answer: Option C. -> Early supplier involvement (ESI)




Question 8. You can create a Production order from?
  1.    Directly from Stock Requirement List
  2.    Using Planned Order
  3.    Both of these
  4.    None
 Discuss Question
Answer: Option C. -> Both of these




Question 9. Material Requirement Planning can be performed at?
  1.    Single Item "“single Level & Plant
  2.    Routing Level
  3.    None of the above
  4.    All of these
 Discuss Question
Answer: Option D. -> All of these




Question 10. In SAP system, Production data structures generated from SAP R/3 master data contains the following data?
  1.    Bill of material
  2.    Master recipe
  3.    Routing
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above




Latest Videos

Latest Test Papers