Total Questions : 1536 | Page 7 of 154 pages
Question 61. Which of the following are the guidelines for the construction of a network diagram?
  1.    Each activity is represented by one and only one arrow in the network
  2.    Dangling must be avoided in a network diagram
  3.    Dummy activity consumes no time or resource
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 62. An activity of the project is graphically represented by ________ on the network diagram.
  1.    A circle
  2.    A straight line
  3.    An arrow
  4.    None of these
 Discuss Question
Answer: Option C. -> An arrow
Question 63. Which of the following statement is correct about the network diagram?
  1.    The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.
  2.    The tail end of the arrow represents the start of an activity.
  3.    The head of the arrow represents the end of an activity.
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 64. Valve analysis is particularly of interest when
  1.    Jobbing work economics are involved
  2.    Production is on large scale
  3.    Only few components are involved
  4.    Costly equipment is used
 Discuss Question
Answer: Option B. -> Production is on large scale
Question 65. Pick up the incorrect statement about advantages of work sampling
  1.    Permits a fine breakdown of activities and delays
  2.    Simultaneous study of many operators may be made by a single observer
  3.    Calculations are easier, method is economical and less time consuming
  4.    No time measuring devices are generally needed
 Discuss Question
Answer: Option A. -> Permits a fine breakdown of activities and delays
Question 66. Statistical quality control techniques are based on the theory of
  1.    Quality
  2.    Statistics
  3.    Probability
  4.    All of the above
 Discuss Question
Answer: Option C. -> Probability
Question 67. According to Rowan plan of wage incentive system, bonus is paid to a worker
  1.    Whose output exceeds 67% efficiency
  2.    On the percentage of time saved
  3.    On the percentage of time worked
  4.    On the percentage of standard time
 Discuss Question
Answer: Option C. -> On the percentage of time worked
Question 68. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker
  1.    Whose output exceeds 67% efficiency
  2.    On the percentage of time saved
  3.    On the percentage of time worked
  4.    On the percentage of standard time
 Discuss Question
Answer: Option A. -> Whose output exceeds 67% efficiency
Question 69. The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as
  1.    Dry work Plan
  2.    Halsey Premium Plan
  3.    Taylor Plan
  4.    Rowan Plan
 Discuss Question
Answer: Option D. -> Rowan Plan
Question 70. The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as
  1.    Rowan Plan
  2.    Taylor Differential Piece rate system
  3.    Halsey Premium plan
  4.    Day work plan
 Discuss Question
Answer: Option C. -> Halsey Premium plan