Question 151. Emergency rush order can be pushed more effectively in
  1.    Job production
  2.    Automatic production
  3.    Continuous production
  4.    Intermittent production
 Discuss Question
Answer: Option D. -> Intermittent production
Question 152. TMU in method time measurement stands for
  1.    Time motion unit
  2.    Time measurement unit
  3.    Time movement unit
  4.    Technique measurement unit
 Discuss Question
Answer: Option B. -> Time measurement unit
Question 153. Slack represents the difference between the
  1.    Latest allowable time and the normal expected time
  2.    Latest allowable time and the earliest expected time
  3.    Proposed allowable time and the earliest expected time
  4.    Normal allowable time and the latest expected time
 Discuss Question
Answer: Option B. -> Latest allowable time and the earliest expected time
Question 154. In steel plant the most important system for materials handling is
  1.    Conveyors
  2.    Cranes and hoists
  3.    Trucks
  4.    Locos
 Discuss Question
Answer: Option D. -> Locos
Question 155. Work study involves
  1.    Only method study
  2.    Only work measurement
  3.    Method study and work measurement
  4.    Only motion study
 Discuss Question
Answer: Option C. -> Method study and work measurement
Question 156. Gantt chart provides information about the
  1.    Material handling
  2.    Proper utilization of manpower
  3.    Production schedule
  4.    Efficient working of machine
 Discuss Question
Answer: Option C. -> Production schedule
Question 157. Pick up the correct statement from the following
  1.    If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
  2.    If the float of an activity is negative, delay in its performance is bound to delay the completion of project
  3.    If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 158. Pick up the correct statement from the following
  1.    Programmer evaluation and review technique is event oriented
  2.    Programmer evaluation and review technique is not event oriented
  3.    Critical path method is event oriented
  4.    None of the above
 Discuss Question
Answer: Option D. -> None of the above
Question 159. Pick up the correct statement from the following
  1.    Critical path method is an improvement upon bar chart method
  2.    Critical path method provides a realistic approach to the daily problems
  3.    Critical path method avoids delays which are very common in bar chart
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 160. Pick up the incorrect statement from the following
  1.    An activity of the project is denoted by an arrow on the net work
  2.    The tail of the arrow indicates the start of the activity
  3.    The head of the arrow indicates the end of the activity
  4.    The arrows are drawn (to scale from) left to right
 Discuss Question
Answer: Option D. -> The arrows are drawn (to scale from) left to right