Question 41. The vertical members fixed between steps and hand rail, are known
  1.    Balusters
  2.    Strings
  3.    Newel posts
  4.    Soffits
 Discuss Question
Answer: Option A. -> Balusters
Question 42. Dampness causes
  1.    Efflorescence
  2.    Bleaching of paints
  3.    Crumbling of plaster
  4.    Growth of termites
 Discuss Question
Answer: Option D. -> Growth of termites
Question 43. While investigating the site, a thick layer of fairly firm clay over a deep layer of soft clay is encountered. In such a situation, the following type of foundation is useful:
  1.    Pile formation
  2.    Raft foundation
  3.    Grillage foundation
  4.    None of these
 Discuss Question
Answer: Option B. -> Raft foundation
Question 44. A temporary rigid structure having platforms to enable masons to work at different stages of a building, is known as
  1.    Scaffolding
  2.    Dead shore
  3.    Raking shore
  4.    Under pinning
 Discuss Question
Answer: Option A. -> Scaffolding
Question 45. The lower edge of the pitched roof, from where the rain water of the roof surface drops down, is known as
  1.    Hip
  2.    Gable
  3.    Ridge
  4.    Eaves
 Discuss Question
Answer: Option D. -> Eaves
Question 46. The lower half portion between crown and skew back of the arch, is called
  1.    Spandril
  2.    Haunch
  3.    Springing
  4.    Soffit
 Discuss Question
Answer: Option B. -> Haunch
Question 47. A floor constructed with 3 mm marble chips, is known
  1.    Mosaic floor
  2.    Terrazzo floor
  3.    Chips floor
  4.    Marble floor
 Discuss Question
Answer: Option B. -> Terrazzo floor
Question 48. As compared to English bond, double Flemish bond is
  1.    Stronger
  2.    More compact
  3.    Costly
  4.    None of the above
 Discuss Question
Answer: Option B. -> More compact
Question 49. In case of Raymond pile
  1.    Lengths vary from 6 m to 12 m
  2.    Diameter of top of piles varies from 40 cm to 60 cm
  3.    Diameter of pile at bottom varies from 20 cm to 28 cm
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 50. A floor constructed with the 4 to 6 mm marble chips, is known
  1.    Reinforced marble floor
  2.    Terrazzo floor
  3.    Marble floor
  4.    Chip floor
 Discuss Question
Answer: Option B. -> Terrazzo floor