Sail E0 Webinar

MCQs

Total Questions : 40 | Page 2 of 4 pages
Question 11. What are are the different scrum events
  1.    Stand-up, Group coding, Back log refinement , Sprint Retrospective
  2.    Daily Scrum, Group coding, Back log refinement , Sprint Retrospective
  3.    Daily Scrum, Sprint Review, Back log refinement , Sprint Retrospective
  4.    Daily Scrum, Sprint Review, Sprint Planning, Sprint Retrospective
 Discuss Question
Answer: Option D. -> Daily Scrum, Sprint Review, Sprint Planning, Sprint Retrospective
Question 12. Which of these isn't a characteristic of Scrum Teams?
  1.    Self-organising
  2.    Experts
  3.    Cross-functional
  4.    Not Applicable
 Discuss Question
Answer: Option D. -> Not Applicable
Question 13. When can a Sprint be canceled?
  1.    The Sprint items are no longer needed
  2.    Sprint can never be canceled
  3.    Whenever the Product Owner says
  4.    Information required to start the development is not available
 Discuss Question
Answer: Option C. -> Whenever the Product Owner says
Question 14. What does a BurnDown Chart display?
  1.    Project Progress
  2.    Amount of remaining work with respect to time
  3.    The velocity of the team
  4.    The capacity of the team members
 Discuss Question
Answer: Option B. -> Amount of remaining work with respect to time
Question 15. If Waterfall is plan driven, then Scrum is:
  1.    PO driven
  2.    Business value driven
  3.    Client driven
  4.    none of the above
 Discuss Question
Answer: Option B. -> Business value driven
Question 16. Product Backlog should be ordered on the basis of?
  1.    Value of the items being delivered
  2.    The complexity of the items being delivered
  3.    Size of the items being delivered
  4.    The risk associated with the items
 Discuss Question
Answer: Option A. -> Value of the items being delivered
Question 17. Which one is not part of the Agile Manifesto?
  1.    Continuous Attention
  2.    Maximize utilization
  3.    Early & Continuous Delivery of Business Value
  4.    Working Daily Together
 Discuss Question
Answer: Option B. -> Maximize utilization
Question 18. What is a key concept behind Agile?
  1.    Plan driven
  2.    Large batches
  3.    Test at the end
  4.    Value and quality driven
 Discuss Question
Answer: Option D. -> Value and quality driven
Question 19. In Scrum, when is a Sprint Over?
  1.    When all the Sprint Backlog Items are completed
  2.    When all the Sprint Backlog tasks are completed
  3.    When the final testing is completed
  4.    When the time box expires
 Discuss Question
Answer: Option D. -> When the time box expires
Question 20. What are the responsibilities of Scrum Master?
  1.    Removing impediments
  2.    Providing process leadership
  3.    None of these
  4.    Both A & B
 Discuss Question
Answer: Option D. -> Both A & B

Latest Videos

Latest Test Papers