  1. X alone can finish a piece of work in 10 days while Y alone can do it in 15 days. If they undertook the job for Rs 225, the share of Y would be

Options:
A .  Rs 75
B .  Rs 80
C .  Rs 85
D .  Rs 85
Answer: Option D