Question
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer: Option A
Was this answer helpful ?
Work done by X in 8 days = \(\left(\frac{1}{40}\times8\right)=\frac{1}{5}\)
Remaining work = \(\left(1-\frac{1}{5}\right)=\frac{4}{5}\)
Now, \(\frac{4}{5}\) work is done by Y in 16 days.
Whole work will be done by Y in \(\left(16\times\frac{5}{4}\right)= 20 days.\)
So, X's 1 day's work = \(\frac{1}{40}\) , Y's 1 day's work = \(\frac{1}{20}\)
(X + Y)'s 1 day's work = \(\left(\frac{1}{40}+\frac{1}{20}\right) = \frac{3}{40}\)
Hence, X and Y will together complete the work in \(\left(\frac{40}{3}\right) = 13\frac{1}{3}days.\)
Was this answer helpful ?
Submit Solution