Sail E0 Webinar
Question

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

Options:
A .  \(13\frac{1}{3}days\)
B .  15 days
C .  20 days
D .  26 days
Answer: Option A

Work done by X in 8 days = \(\left(\frac{1}{40}\times8\right)=\frac{1}{5}\)


Remaining work = \(\left(1-\frac{1}{5}\right)=\frac{4}{5}\)


Now,   \(\frac{4}{5}\)  work is done by Y in 16 days.


Whole work will be done by Y in \(\left(16\times\frac{5}{4}\right)= 20 days.\)


So, X's 1 day's work =  \(\frac{1}{40}\) , Y's 1 day's work = \(\frac{1}{20}\)  


(X + Y)'s 1 day's work = \(\left(\frac{1}{40}+\frac{1}{20}\right) = \frac{3}{40}\)


Hence, X and Y will together complete the work in \(\left(\frac{40}{3}\right) = 13\frac{1}{3}days.\)


Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

More Questions on This Topic :


Latest Videos

Latest Test Papers