Which of the following statement is wrong about the internal silting method?
Options:
A .  The extra strength is gained by increasing the section of the banks
B .  The additional soil is derived from the natural process of silting internally
C .  This method of strengthening the canal is very cheap, simple and efficient
D .  To decelerate the silting process low submersible spurs may be constructed
Answer: Option D
Answer: (d).To decelerate the silting process low submersible spurs may be constructed