Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Options:
A .  The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B .  The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C .  Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D .  All the above
Answer: Option D