Sail E0 Webinar
Question
In the budget hierarchy, the material handling cost is
Options:
A .  fixed manufacturing cost
B .  batch level cost
C .  per unit cost
D .  factory overall cost
Answer: Option B
Answer: (b).batch level cost

Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers