In cpm, the cost slope is determined by
Options:
A .   Crash cost/Normal Cost
B .   (Crash Cost - Normal cost)/ (Normal time - Crash time)
C .   Normal Cost/Crash cost
D .   (Normal cost - Crash cost)/ (Normal time - Crash time)
Answer: Option B
Explanation :