If the actual price input is $700, the budgeted price of input is $400 and the actual quantity of input are 50 units, then the price variance will be
Options:
A .  $15,000
B .  $13,000
C .  $11,000
D .  $9,000
Answer: Option A
Answer: (a).$15,000