If P, Y and Z are the weights of cement, fine aggregates and coarse aggregates respetively and W/C is the water cement ratio, the minimum quantity of water to be added to first batch, is obtained by the equation
Options:
A .  0.1P + 0.3Y + 0.1Z = W/C x P
B .  0.3P + 0.1Y + 0.01Z = W/C x P
C .  0.4P + 0.2Y + 0.01Z = W/C x P
D .  0.5P + 0.3Y + 0.01Z = W/C x P
Answer: Option B Answer: (b).0.3P + 0.1Y + 0.01Z = W/C x P