If Mr. Shyam pays the workers Rs. 3040 in all for this job, how many workers work on day 3?
Options:
A .  3
B .  2
C .  4
D .  Cannot be determined
Answer: Option A
:
A
The man-hours required for the job =(304020)=152.
The Total number of workers who worked on this job for 6 days =(1528)=19.
We get the following possibilities for the number of workers:
Day1Day2Day3Day4Day5Day6323434343234