If Milind decides to complete 30 Aakruti shirts only and no other on a particular day, how many total man-hours will be idle?
To complete 30 AAKRUTI shirts
Time consumed by Cutters = (30 × 30) = 900 mins
Time consumed by tailors = (30 × 60) = 1800 mins
Time consumed by assistants = (30 × 30) = 900 mins
Time available for cutters = (1200 – 900) = 300 mins
Time available for tailors = (3000 – 1800) = 1200 mins
Time available for Assistant = (1200 – 900) = 300 mins
As they are not working in this available time it is the idle time.
Hence total man hours that are idle = (300 + 1200 + 300) = 1800 mins = 30 hours.