Question


If Mr. Shyam pays the workers Rs. 3040 in all for this job, how many workers work on day 3?


Options:
A .   3
B .   2
C .   4
D .   Cannot be determined
Answer: Option A
:
A

The man-hours required for the job =(304020)=152.


The Total number of workers who worked on this job for 6 days =(1528)=19.


We get the following possibilities for the number of workers:


Day 1Day 2Day 3Day 4Day 5Day 6323434343234