Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same
Options:
A .  A is correct but R is not correct
B .  R is correct but A is not correct
C .  Both A and R is correct
D .  Both A and R is incorrect
Answer: Option A