Question
Arun can finish a work in 12 days; Ajit can finish the same work in 15 days while Amit can finish the same work in 20 days. Find the total time taken when all three work together to complete the work.
Options:
A .  6 days
B .  5 days
C .  4 days
D .  3 days
Answer: Option B
:
B
Arun can finish 100% of work in 12 days he can finish (10012)=8.33%of the work in a day.
Ajit can finish 100% of work in 15 days he can finish (10015)=6.67% of the work in a day.
Amit can finish 100% of the work in 20 days he can finish(10020)=5% of the work in a day.
So, if all three work together, then they can finish (8.33+6.67+5)%=20% of the work in a day.
So, they can complete the work in (10020)= 5 days. Hence option (B).
2nd method:- W= 12A=15B=20C .
n(A+B+C)=12A,n(A+34A+35A)=12A,n=5days.
Option (2).

Was this answer helpful ?
Next Question

More Questions on This Topic :


Share this page with your friends!

Latest Videos

Cube & Cuboid Part 1 Reasoning (Hindi)
Data Interpretation (DI) Part1 Basic Concepts Reasoning (Hindi)
Counting Figures Part 1 Counting Of Straight Lines Reasoning (Hindi)
Direction Sense Test Part 1 Reasoning (Hindi)
Chapter 1 - GLOBAL STEEL SCENARIO & INDI Part 1 : (13-04-2024) ICA 2024
Chapter 1 - RMHP / OHP / OB & BP Part 1 : (14-02-2024) GPOE 2024
Real Numbers Part 7 Class 10 Maths

Latest Test Papers

Test paper 1 Reasoning & DI
Chapter 1.1 : INTRODUCTION GPOE/GPA 2024
Chapter 1.1 : Personnel Functions- An overview GFM 2024
Chapter 3.1 : INTRODUCTION GPOE/GPA 2024
Chapter 2.3 : COAL HANDLING PLANT - Set 1 GPOE/GPA 2024