Sail E0 Webinar
Question
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
Options:
A .  0.50
B .  0.66
C .  0.84
D .  0.95
Answer: Option C

Submit Your Solution Below and Earn Points !
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers